Skip to content

Tribes press judge to halt US-Canada pipeline as work starts

BILLINGS, Mont. — Native American tribes and environmental groups pressured a federal judge on Thursday to shut down work on the disputed Keystone XL pipeline from Canada to Nebraska, citing fears workers could spread the coronavirus and construction could damage land.

After years of delays, the company is rushing ahead amid the pandemic to get part of the line built so it will be harder to stop, attorneys for the project's opponents argued in a teleconference to decide if the construction should be halted.

They warned that plans to build construction camps housing up to 1,000 workers each pose a risk to tribes and rural communities that already struggle to provide basic health care services and would face challenges responding to coronavirus outbreaks.

The first U.S. segment of the 1,200-mile (1,900-kilometre) oil sands pipeline was installed by TC Energy this week across the Canada border in northern Montana. The fight over the line stretches back more than a decade after it became a lightning rod in the debate over fossil fuels’ contribution to climate change.

“With the rise of the pandemic, it is even more important to protect the tribe to at least put a pause on this activity, take hard look at this,” said Matthew Campbell, an attorney for the Native American Rights Fund representing the Rosebud Sioux Tribe of South Dakota and the Assiniboine and Gros Ventre tribes of the Fort Belknap reservation in Montana.

President Donald Trump is a champion of the $8 billion project and gave it a presidential authorization in a bid to circumvent a 2018 court ruling that had blocked it.

The same judge who made that ruling, U.S. District Judge Brian Morris in the Montana city of Great Falls, presided over Thursday's hearing, which also included arguments over whether Trump's authorization was legal.

Late Wednesday, Morris handed another setback to TC Energy with a ruling that invalidated a key U.S. Army Corps of Engineers clean water permit. The so-called nationwide permit applied to a broad range of projects including Keystone XL, and is needed to so the pipeline can cross rivers, streams and other waterways.

Keystone XL would have hundreds of those crossings along its 1,200-mile (1,930 kilometre) route from Hardisty, Alberta to Steele City, Nebraska. It would carry up to 830,000 barrels (35 million gallons) of crude daily and opponents say a spill is inevitable.

Workers on Monday installed the first section of pipe across the U.S.-Canada border in northern Montana, according to court documents filed by the Calgary-based company.

The border crossing doesn't require the Army Corps permit that was thrown out because there are no nearby waterways. But it's an obstacle to much further work, and a company spokesman warned the judge's ruling has broad implications for projects across the U.S.

“The ruling directly impacts various utilities constructing and maintaining infrastructure projects, including natural gas, liquids, television cable, electrical transmission, telephone, internet, among others," pipeline spokesman Terry Cunha said. “This decision hampers their ability to build or maintain infrastructure projects in wetlands and water bodies across the U.S."

The Army Corps referred questions to U.S. Justice Department spokesman Wyn Hornbuckle, who said government attorneys were evaluating options but provided no further details.

TC Energy plans to drill tunnels for the pipeline deep beneath major river crossings and says it will be operated safely. The company has a history of spills from other oil pipelines it operates, including a 2017 accident near Amherst, South Dakota that spilled almost 10,000 barrels (407,000 gallons) of oil.

TC Energy’s surprise March 31 announcement that it planned to start construction on Keystone XL amid a global economic crisis caused by the coronavirus pandemic came after the provincial government in Alberta invested $1.1 billion to jump-start the work.

Tribal leaders and some residents of rural communities along the pipeline’s route worry thousands of workers needed for the project could spread the virus in small communities that are unprepared.

TC Energy wants to “use this construction as justification for allowing the project to proceed whether or not it is legal,” the tribes' attorney said.

As many as 11 construction camps, some housing up to 1,000 people, were initially planned for the project. TC Energy says those are under review amid the pandemic and won’t be needed until later in the summer.

For most people, the coronavirus causes mild or moderate symptoms, such as fever and cough, that clear up in two to three weeks. For some, especially older adults and people with existing health problems, it can cause more severe illness, including pneumonia and death.

The rural counties along the pipeline's route so far have seen far fewer infections than other parts of the U.S. But they lack adequate health care services to deal with a large outbreak.

Construction on two worker camps could start as soon as this month in Montana and South Dakota, according to court documents filed by the company.

The construction under way in Montana involves about 100 workers. It's exempted from Democratic Gov. Steve Bullock’s March 26 “stay at home” directive, which is aimed at preventing the spread of the virus by discouraging many daily activities, according to state officials.

The directive did not address worker camps. Bullock spokeswoman Marissa Perry said the governor wants all coronavirus concerns addressed before TC Energy finalizes its plans in areas requiring camps.

___

Follow Matthew Brown at https://twitter.com/matthewbrownap

Matthew Brown, The Associated Press

push icon
Be the first to read breaking stories. Enable push notifications on your device. Disable anytime.
No thanks